Project or Investment Bankability Check for Tanzania: Free Scorecard | TICGL
TICGL Home/Bankability/Bankability Check
TICGL/TERI - Free investment-readiness tool
TICGL/TERI ToolsFreeProject FinanceBankability

Project or Investment Bankability Check for Tanzania: A Free 0–100 Scorecard

Many Tanzanian projects have willing investors and still never reach financial close. The reason is rarely the idea; it is whether the numbers, the funding structure, the land, the contracts and the preparation hold up when a lender or investor looks at them. Enter your project's details below and the scorecard returns a 0–100 bankability score, your debt-service cover and returns, the funding gap to close, red flags, and the changes that would lift your score the most. It is free, it runs in your browser, and nothing is sent to us unless you choose to e-mail your result.

🆓 Free🔒 Private: runs in your browser🏛️ TICGL / TERI📖 Benchmarks: TICGL/TERI Bankability–Affordability report, Oct 2026
Dimensions scored
8 100-point scale
Debt-service cover reference
1.3x lenders: 1.2–1.4x
Return benchmark
16% bond 10.8%
Affordability test
70% users able to pay

This is a screening tool, not a credit rating, loan approval or financial advice. Results depend entirely on the inputs you enter. A real lender will test your project against its own criteria.

Why Bankability Matters

A project is bankable when a lender or investor will fund it on commercial terms, because its cash flow can repay them with a safe margin, its return beats the alternatives, and its land, contracts, permits and preparation hold up under scrutiny. Financing is the gate between a plan and a built project, so testing bankability early shows what a lender will find while it is still cheap to fix.

It decides whether money arrives

Lenders test cash-flow cover, returns, structure, contracts and legal title. A weakness in any one of them can stop financial close, however good the idea.

It protects your budget and time

Feasibility studies, designs and approvals cost money. A short check before you spend shows which gap to close first, instead of discovering it at the lender's desk.

It fits the project you have

A private factory and a public market need different things. Grants, VGF and PPP support are scored only where your project depends on them; commercial projects are not penalised for not needing them.

Why Tanzanian Projects Struggle to Reach Financial Close

TICGL/TERI research finds that many projects in Tanzania look viable on paper but fail at financing. The recurring causes are structural, not a lack of ideas or interested investors:

  • The price that repays capital is not the price users can pay. In the TICGL/TERI local-authority markets case, the rent needed to repay commercial capital was about TZS 58,200 per m² a month, against a median stated affordability of about TZS 8,300.
  • Expensive, short debt. Local-currency lending is costly against a government bond yield of about 10.8%, so cash flow must clear a high bar before it can service a loan.
  • Thin capital stacks. Equity is often not committed in writing, and long-tenor funding that matches the life of the asset is scarce.
  • Land, permits and contracts left late. Unregistered or contested rights, missing approvals and no contracted revenue stop lenders even when the numbers look acceptable.
  • Preparation gaps. Studies without a reviewed financial model, and public support such as VGF or guarantees that is assumed but not secured.

The check below tests exactly these points, so you can see where your project stands before a lender does.

Read first: the research behind this scorecard

The tests in this tool come from TICGL/TERI's work on why Tanzanian projects fail to reach financial close and who pays when a project must repay its lenders.

Project Finance in Tanzania →Beyond Bankability: The Capital Stack →The Bankability–Affordability Dilemma →

01 — Your ProjectEnter Your Project's Details

Use your best current numbers. If you do not know a figure yet, use a realistic estimate, because that gap in knowledge is itself something a lender will notice. All money figures are in TZS million. You can load an illustrative example first to see how the tool behaves.

Load an illustrative example:

Examples use illustrative figures shaped like the TICGL/TERI LGA market case; they are not real projects.

A · Project basics

TICGL/TERI base case 16%; 12% concessional; 18% stressed.

B · Cost and funding (TZS million)

Public or concessional capital that does not need repayment.
Share of the equity you need that is committed in writing or cash.
A foreign-currency loan repaid from shilling revenue carries exchange-rate risk.

C · Operations (TZS million)

Use year-1 revenue at stabilised occupancy or volume.
Include maintenance and management. Pre-tax view.
TICGL/TERI screen: at least 70% for the commercial layer. Applies when ordinary users or small businesses pay.
If your buyers are large companies or a creditworthy offtaker under contract, the 70% affordability test is switched off and demand is scored on evidence alone.

D · Demand, contracts, land and permits

E · Preparation, sponsor and risk

02 — Your ScoreYour Bankability Result

–
out of 100
–

Minimum DSCR
–
lenders: about 1.2–1.4x
Average DSCR
–
over the loan tenor
Loan life cover (LLCR)
–
PV of cash flow ÷ debt
Project IRR (pre-tax)
–
vs hurdle
Equity IRR (pre-tax)
–
after debt service
Payback
–
years, unlevered
Debt
–
TZS million
Equity needed
–
TZS million

Score by Dimension

0–100 for each of the eight dimensions. Green 75+, slate 55–74, amber 35–54, rust below 35

Cash Flow vs Debt Service

TZS million a year (bars, left axis) and DSCR (line, right axis). Dashed: 1.3x reference

Red flags and strengths

    The gap to bankable

    Highest-impact moves

    Each bar shows how many score points your result would gain if you made that one change, with everything else unchanged. Start at the top.

    Score Gain From One Change

    Points added to your 0–100 score. TICGL/TERI scoring model

    How Much Public Capital Moves the Score?

    Score (left axis) and minimum DSCR (right axis) as grant or VGF share of cost rises from 0% to 80%, other inputs unchanged

    Priorities, in plain words

      03 — How We ScoreThe Eight Dimensions, the Benchmarks and the Limits

      The score combines a small cash-flow model with how complete and secure the project's foundations are. Weights reflect what typically stops Tanzanian projects at financial close: weak cash-flow margin and returns, an unsecured funding structure, unproven demand and affordability, missing land, permits or contracts, thin preparation, and unmanaged risk.

      DimensionWeightWhat is testedBenchmark used
      A · Cash-flow strength20Minimum DSCR and loan life cover over the loan tenorDSCR 1.3x (lenders commonly 1.2–1.4x); below 1.0x cash flow cannot repay debt
      B · Returns vs cost of capital10Project IRR against your hurdle and the government bondHurdle 16% (base); 15-year bond about 10.8%
      C · Capital structure and funding12Debt share, tenor against asset life, equity secured, currency matchDebt about 70% or less of financed cost; tenor within about 60–80% of life; foreign-currency debt against shilling revenue penalised
      D · Demand and affordability15Share of target users able to pay; strength of demand evidenceAt least 70% able to pay (TICGL/TERI affordability screen)
      E · Contracts and pricing10Customer contracts or pre-lets; approved pricing or tariff frameworkLong-term contracts for most revenue; approved indexation
      F · Land, permits and legal10Secured land rights; approvals and certificatesClean, mortgageable title; main approvals in hand
      G · Preparation and sponsor13Stage of studies; sponsor track record and capacityIndependent feasibility with a reviewed financial model
      H · Risk, ESG and public support10Environmental and social work; status of any VGF, guarantee or concessionESIA approved; signed support where the project needs it

      Rating bands

      75–100
      Lender-ready
      Strong enough to approach lenders and investors, with no critical red flags
      55–74
      Conditionally bankable
      Credible, with specific gaps to close first
      35–54
      Not yet bankable
      Material gaps in cash flow, structure or preparation
      0–34
      Concept stage
      Needs preparation before any financing conversation
      Critical red flags cap the rating

      A minimum DSCR below 1.0x caps the score at 49. Any of these also caps the score at 69, so a project cannot be rated lender-ready with them present: project IRR below the government bond yield, fewer than half of target users able to pay, no secured land rights, or less than 30% of required equity secured.

      Projects that need no grant, VGF or PPP support

      Scored on what they actually need

      If you choose "Not needed" for public support, dimension H is scored on environmental and social work alone, so a fully commercial project is not marked down for lacking VGF or a PPP agreement. A grant share of 0% is not penalised. If your buyers are corporate customers or a creditworthy offtaker, choose that option in Tab 1 and the 70% affordability test is switched off. Land, permits, contracts, cash-flow cover and returns are tested for every project.

      The model in brief

      // Financed cost, debt and equity
      Financed cost = Project cost × (1 − grant %)
      Debt = Financed cost × debt %  ·  Equity = Financed cost − Debt

      // Debt service (level annuity over the tenor) and cover
      Debt service = Debt × r ÷ (1 − (1 + r)−tenor)
      Cash flow available for debt service (CFADS) = Revenue × (1 − operating-cost %)
      DSCR = CFADS ÷ Debt service  ·  LLCR = PV of CFADS over tenor ÷ Debt

      // Funding gap to a 1.3x DSCR
      Grant share needed = 1 − (1 − current grant %) × minimum DSCR ÷ 1.3
      What this tool cannot do

      It is a first screen. It ignores tax, construction-period interest, inflation, working capital, taxes on distributions, phasing and detailed risk allocation, and it uses level debt repayments. Qualitative answers are self-reported. A bank or investor will apply its own criteria, and the TICGL/TERI research shows that the same project can look bankable on a lender's terms and unaffordable to its users. For that reason affordability is scored explicitly. Read the underlying research in The Bankability–Affordability Dilemma.

      04 — Get It BankableFrom a Free Score to a Financeable Project

      The scorecard shows where the gaps are. Closing them takes preparation work that lenders and investors will check: studies, a financial model, a funding structure, and evidence of demand and affordability. TICGL (Tanzania Investment and Consultant Group Ltd), with its research arm TERI, prepares projects for financing and has delivered feasibility studies for PPP projects including the Boko Dawasa bus terminal and the Msasani Fish Market redevelopment.

      1 · Free screening

      • This scorecard.
      • Score, red flags, funding gap and ranked fixes.
      • No cost, no obligation.

      2 · Bankability gap review

      • TICGL economists review your result and documents.
      • Independent view of the gaps and what lenders will ask.
      • A short written action plan.

      3 · Project preparation

      • Feasibility study across market, technical, financial and economic, legal, environmental and social, and risk.
      • Financial model with DSCR, NPV, IRR and downside cases.
      • Demand and willingness-to-pay research.

      4 · Structuring and financing support

      • Capital stack, VGF and PPP structuring.
      • Lender and investor packs.
      • Entry-mode, registration, TIC incentive and approvals support.

      What usually moves a score the most

      Typical gapWhat closing it involves
      DSCR below 1.3xRevisit pricing and volumes with evidence, cut cost or phase the build, extend tenor, lower the interest rate, and size debt to cash flow; if a funding gap remains, name its source (grant, VGF or equity).
      Users cannot afford the priceTest willingness and ability to pay with a proper survey, tier the pricing, separate the public-good core from the commercial layer, and show a pass-through table.
      Equity or land not securedObtain written equity commitments and registered land rights before approaching lenders.
      No independent feasibility studyCommission a feasibility study with a reviewed financial model, which lenders and the PPP Centre expect.
      Currency mismatchMatch the currency of debt to the currency of revenue, or add hedging and a reserve.
      No contracts or approved tariffsSecure pre-lets, offtake or approved pricing with indexation.

      Talk to TICGL/TERI

      Send us your result, or book a conversation about preparing your project for financing.

      ✉️ economist@ticgl.comBook a consultation →What We Do →TICGL Markets →TERI Research →

      05 - Quick AnswersFrequently Asked Questions

      What does bankable mean for a project in Tanzania?

      A project is bankable when its expected cash flow can repay lenders with a safe margin, it earns a return above the cost of capital, its funding structure is secured, and its land, permits, contracts and preparation are strong enough for a lender or investor to commit. A profitable project is not automatically bankable.

      Is the TICGL bankability scorecard free and private?

      Yes. The scorecard is free. All calculations run in your browser and nothing is sent to TICGL unless you choose to e-mail your results.

      What debt-service cover ratio do lenders expect?

      Lenders commonly test a debt-service cover ratio (DSCR) of about 1.2 to 1.4 times. The scorecard uses 1.3 times as its reference. A minimum DSCR below 1.0 means cash flow cannot cover debt payments.

      What score makes a project bankable?

      A score of 75 or more with no critical red flags is rated lender-ready; 55 to 74 is conditionally bankable with gaps to close; 35 to 54 is not yet bankable; below 35 is at concept stage. Critical red flags cap the rating.

      Why can a profitable project still fail the bankability test?

      Profit is not the same as the ability to service debt on schedule. Lenders also test cash-flow margin, tenor, equity commitment, currency match, land title, permits, contracts and the quality of the feasibility study.

      What if my project depends on charges that users may not be able to afford?

      Enter the share of target users who can pay your proposed price. TICGL/TERI research on LGA markets and bus terminals shows that affordable charges often cover only a fraction of capital cost, and that the gap moves to users, taxpayers or investors rather than disappearing.

      How can TICGL help improve my project's bankability?

      After the free screening, TICGL offers paid services: a bankability gap review, feasibility studies and financial models, PPP and viability-gap structuring, and lender or investor packs.

      Muhtasari

      Muhtasari kwa Kiswahili

      Je, mradi wako unakopesheka (bankable)? Pima bure kwa dakika tano. Miradi mingi ya Tanzania ina wawekezaji wanaotaka kuingia lakini haifikii hatua ya kupata fedha. Sababu mara nyingi si wazo la mradi, bali kama hesabu, muundo wa ufadhili, ardhi, mikataba na maandalizi vinasimama mbele ya benki au mwekezaji. TICGL/TERI imetengeneza kipimo cha bure ambacho unaingiza taarifa za mradi wako na kupata alama ya 0 hadi 100.

      Kinapima nini: vipengele nane: nguvu ya mtiririko wa fedha (DSCR), mapato dhidi ya gharama ya mtaji, muundo wa mtaji, mahitaji na uwezo wa watumiaji kulipa, mikataba na bei, ardhi na vibali, maandalizi na uzoefu wa mwendeshaji, na hatari, mazingira na msaada wa umma.

      Vigezo: DSCR ya mara 1.3 (benki kwa kawaida hutaka mara 1.2 hadi 1.4), mapato ya asilimia 16 yanayotakiwa kwa mwekezaji dhidi ya hatifungani ya miaka 15 yenye takriban asilimia 10.8, na angalau asilimia 70 ya watumiaji walengwa waweze kulipa bei yako.

      Utapata nini: alama, DSCR na IRR, pengo la ufadhili unalohitaji kuziba, alama nyekundu, na orodha ya hatua zenye athari kubwa zaidi. Ukiona DSCR iko chini ya mara 1.0, mradi hauwezi kulipa deni kutokana na mtiririko wake wa fedha.

      Faragha na mipaka: hesabu zote hufanyika kwenye kivinjari chako na hakuna kinachotumwa kwa TICGL isipokuwa ukichagua kututumia matokeo kwa barua pepe. Hiki ni kipimo cha awali, si tathmini ya mkopo wala ushauri wa kifedha.

      Hatua inayofuata: baada ya kipimo cha bure, TICGL/TERI hutoa huduma za kulipia: mapitio ya mapengo ya bankability, upembuzi yakinifu (feasibility) na modeli ya kifedha, kupanga muundo wa PPP na VGF, na kuandaa nyaraka kwa benki na wawekezaji.

      Hitimisho: mradi wenye faida si lazima uwe unakopesheka. Kinachoamua ni uwezo wa kulipa deni kwa wakati, mtaji uliothibitishwa, na maandalizi yanayoweza kuthibitishwa. Wasiliana: economist@ticgl.com.

      Chanzo: TICGL/TERI, Bankability–Affordability Dilemma (Oktoba 2026); vigezo vya DSCR na mapato vimetumika kama marejeo ya awali.